Well the day has arrived 1000hrs 28th January 2013......the Pater Hall refurbishment begins.....remember we are managing to honour all our bookings although there may be some shuffling of resources.

 

There will be few changes to  events in the hall during the works with the exception of the relocation of the Credit Union to the "Council" entrance in Lewis Street on Tuesdays, and for the next three months Council Meetings will be in the Warrior Suite.

 

When finished the Main Hall will be a great place for your events, new cloakrooms including disabled facilities a servery open to the main hall....for drinks and refreshments...a new kitchenette on the first floor. The works will also include a new ramped entrance to the hall reception area from Lewis Street a control room and at last an office for the Pater Hall Trust

 

 

Day one..................not much to show yet

Day two..................whoops sorry my hammer slipped

Day Four..................Its all happening.....upstairs....not able to show you today

Day Eleven..............all holes and lintels

Day sixteen........a lack of steps too far

Day eighteen..........more holes ...but some rebuilding

Day 24........As one door closes....another one opens

Day 30.................All smiles at first site meeting

 

More....Just a click away

 

                           


Day 30.................All smiles at first site meeting

 

 

 

 

 

New holes.....the bar servery.............the control room

Ready for the floor for new kitchen on the 1st floor.......if you see what I mean


Day 24........As one door closes....another one opens

 

 

  New entrance from Lewis Street..soon

 

Servery...to Main Hall  Old fire door to Lewis Street....blocked up

 

Van man!!!!!!!!!


 

Day eighteen..........more holes ...but some rebuilding

 

 

 

 

 

 

 

 

 

 


 

Day sixteen........a lack of steps too far

 

 

Soon to be "the bar" in the Main Hall

 

What no loo's !...................

 

............Or Stairs

 

....Soon to be a new floor..............

 

 

Day Eleven..............all holes and lintels
 

 

Control room opening to Main Hall

 

Opening for the building of the survey into the main hall.

 

New door in the main hall

 

Open ready for the new hallway 1st floor

 

New door into the Meyrick Owen Suite

 

New projection/control room opening

 

 


 

 

 

 

 

 

 

Day Four..................Its all happening.....upstairs....not able to show you today

 

 

 

 


 

 

Day two..................whoops sorry my hammer slipped

 

 

 

 

 


 

Day one..................not much to show yet

 

 

 

 

 

 

 

 

 

 